  Oregon Evaluation Plan
The proposed timeline for the evaluation is as follows:
  March 31, 2009 - Criteria and standards for study developed.
 
June 15, 2009 - RFP developed and circulated to potential vendors.
 
July 31, 2009 - Response to RFP due from potential vendors.
 
August 1-31, 2009 - Responses reviewed by group, potential evaluators
interviewed.
 
By Sept 8, 2009 - Evaluator selected.
 
October 15, 2009 - Evaluation begins.
 
March 15, 2010 - Evaluation Completed.