Construction Ahead

Construction Projects

Cascade Natural Gas Corporation is in the process of replacing and updating service lines within our service territory. This is an ongoing program to ensure our customers safe and efficient natural gas service now and well into the future.

As a result of this construction, you may see some disruption of your normal traffic routes during the day. This construction activity will be kept as minimal as possible and will be cleaned up daily. Customers within the area of the replacement will be contacted regarding updating their lines and meters as the construction crew draws near. See below for more details about construction in your area.

Shelton, WA Pipeline Replacement Project -  (Phase 2)

Construction on Phase II of the natural gas pipeline replacement project is tentatively scheduled to begin April 23 and conclude in late July 2018, weather pending.

For more information, please contact us by email at customerservice@cngc.com, or by phone at 888-522-1130, or speak with our field personnel on site at any time. We are committed to our community and your input is very important to us. All inquiries are welcome and will be answered promptly

See the outlined area on the map below for more detail on streets affected.  Click on the map for a closer view.  

Bend, OR - Westside Replacement Project (Phase 7)

Phase 7

Cascade Natural Gas Corporation is starting the Bend Westside Replacement Project Phase 7, Section 1/NW 14th Street on Monday 3/26/18. Crews will set up a traffic detour from NW Galveston Ave./NW Skyliners Rd. west to NW MT Washington Dr. Then north up NW MT Washington Dr. to NW Shevlin Park Rd./NW Newport Ave., and east on NW Shevlin Park Rd/ NW Newport Ave to NW 14th St. Once the traffic detour is in place, traffic on NW 14th Street south bound between NW Newport Ave. & NW Galveston Ave. will be closed to all traffic from March 26, through June 8, 24 hours a day. North bound traffic will remain open on NW 14th St. The south bound lanes will be used for construction equipment. The current plan is to open up traffic in both directions for the Memorial Day weekend and return to the current traffic plan until completion of Cascade’s current scope of work. For more about the NW 14th street Improvement project: www.BendOregon.gov/14thStreet.

Phase 7 Update

Crews working on the Bend Westside Replacement Project Phase 7 Section 1,  as of Thursday 4/12/18, reached NW Jackson Ave. & NW 14th St. The rock hammer/excavation crew will begin crossing NW Jacksonville Thursday 4/12/18. The pipe crew is currently at the intersection of NW 14th St. and the alley between NW Ithica Ave. & NW Jacksonville Ave. They will be there for a couple of days installing infrastructure. South bound traffic on NW 14th St. will continue to be closed until June 8, 2018.

Phase 7 Update

Crews working on the Bend Westside Replacement Project Phase 7 Section 1 have reached NW Ithica Ave. & NW 14th St, as of 4/6/18. Crews will continue working north on NW 14th St. Southbound traffic on NW 14th St continues to be closed.

Phase 7 Update

Crews working on the Bend Westside Replacement Project Phase 7 Section1 are removing trees in the pathway of the new gas main on NW 14th St. The excavation crews are exposing the 2-inch tie-in points in the alleys on the west side of NW 14th and are trenching north on NW 14th St. The excavation crew working on trenching on NW 14th St should cross NW Hartford Ave Saturday, 3/31/18. NW 14th St continues to be closed to southbound traffic.

Detour route noted in yellow:

Phase 7

Bend, OR - Pipeline Replacement (Phase 6)

Phase 6 Sections 1-2
Pipeline installation has been completed; asphalt and concrete restoration has been suspended until spring 2018.

Phase 6 Section 3 Update
Crews working on the pavement restoration on Bend Westside Replacement Project Phase 6 Section 3 are mid-block on NW Staats St. between NW Georgia Ave. & NW Florida Ave. Weather permitting, they should reach NW Florida on Friday, 4/6/18, and cross NW Florida Ave. Monday, 4/9/18, and continue toward NW Delaware Ave.  

Phase 6 Section 3 Update
Paving and final restoration on Bend Westside Replacement Project 3 Phase 6 Section is scheduled to begin Tuesday, 4/3/18. The paving crews will start at the intersection of NW Kansas Ave. & NW Staats St. and work south toward NW Delaware Ave. It is estimated to take about a week to reach NW Delaware Ave. Once the paving crews have reached the tie-in point on NW Staats St. between NW Delaware Ave. and NW Colorado Ave., the paving crews will move to the intersection of NW Georgia Ave. & NW Bond St. and work east.

Pendleton, OR Pipeline Replacement Project -  (Phase 1)

Construction is expected to conclude by the end of January, 2018.  If you have any questions, please contact us by phone at 1-888-522-1130, email at customerservice@cngc.com or speak with our field personnel on site at any time.  We are committed to our community and your input is very important to us.

See the outlined area on the map below for more detail on streets affected.  Click on the map for a closer view.  


Online Account Services

3 Choices Online Account