Construction Ahead

Construction Projects

Cascade Natural Gas Corporation is in the process of replacing and updating service lines within our service territory. This is an ongoing program to ensure our customers safe and efficient natural gas service now and well into the future.

As a result of this construction, you may see some disruption of your normal traffic routes during the day. This construction activity will be kept as minimal as possible and will be cleaned up daily. Customers within the area of the replacement will be contacted regarding updating their lines and meters as the construction crew draws near. See below for more details about construction in your area.

Bend, OR - Pipeline Replacement (Phase 6)

October 19, 2017

Phase 6 Sections 1-2
Paving crews working on Bend Westside Replacement Project, Phase 6 Sections 1-2 will move into Section 3 on Monday 10/23/17. The paving crew will  start at the intersection of NW Broadway St. & NW Georgia Ave. and will work east. NW Georgia Ave. will remain closed to through traffic during paving operations from 7 a.m. to 5 p.m. and will be open to traffic each evening.

 
Phase 6 Section 3
Construction crews working on Bend Westside Replacement Project, Phase 6 Section 3 have moved into the gravel alley between NW Florida Ave. & NW Delaware Ave. and are installing a 2-inch natural gas main and services. Crews are working west in this alley and should cross NW Wall St. on or about 10/18/17. The alley between NW Florida Ave. & NW Georgia Ave. will remain closed  to through traffic between 7 a.m. and 5:30 p.m. and will be open each evening.

   
October 12, 2017

Phase 6 Sections 1-2-3
Construction crews working on Bend Westside Replacement Project, Phase 6 Section 3 have moved into the gravel alley between NW Florida Ave. & NW Delaware Ave. and are installing a 2-inch natural gas main and services. Crews are working west in this alley and should cross NW Wall St. on or about 10/18/17. The alley between NW Florida Ave. & NW Georgia Ave. will remain closed  to through traffic between 7 a.m. and 5:30 p.m. and will be open each evening.

Paving crews working on Bend Westside Replacement Project, Phase 6 Sections 1-2 (as of  Thursday 10/12/17) are paving on NW Riverside Blvd. working toward NW Congress St. The paving crews will reach the intersection of NW Congress St. & NW St. Helens Place on Friday 10/13/17. The paving crews will then continue paving on NW Congress St. toward NW Tumalo Ave. NW Congress St. will remain closed to through traffic during paving operations from 7 a.m. to 5 p.m. and will be open to traffic each evening.




For a detailed map of phase 6 of the project click here or see the image below.
Note: the attached map shows section 2 highlighted in green and section 1 highlighted in purple.

Bend OR, Phase 6 map

Pendleton, OR Pipeline Replacement Project -  (Phase 1)

October 20, 2017
Construction is scheduled to begin the first week of October and complete in December 2017.  If you have any questions, please contact us by phone at 1-888-522-1130, email at customerservice@cngc.com or speak with our field personnel on site at any time.  We are committed to our community and your input is very important to us.

See the outlined area on the map below for more detail on streets affected.  Click on the map for a closer view.  

Longview Washington (Broadway Neighborhood), WA -  Phase 6 is tentatively scheduled

June 14, 2017

Construction on Phase 6 of the pipeline replacement project is tentatively scheduled to begin June 26th and complete in Mid November.

See the outlined areas on the map below for more detail on the streets affected. Click on the map for a closer view. For more information, please contact us by email at BendReplacementProject@cngc.com, or by phone at (360) 577- 4812, or speak with our field personnel on site at any time. We are committed to our community and your input is very important to us. All inquires are welcome and will be answered promptly.

Map of area affected by Longview, WA Pipeline Upgrade Project



Online Account Services

3 Choices Online Account

Anacortes, WA - Anacortes Pipeline Replacement Project (Phase 4)

January 19, 2017

Phase 4 of the Anacortes Replacement project is nearing completion.  Work is currently being performed to tie individual service lines into the new gas main.  We anticipate that all customers within the project area will be connected by the beginning of February 2017. 

Inclement weather has slowed the repair of asphalt and concrete surfaces.  We anticipate completing the repair of these hard surfaces by the end of March 2017.

Please direct any concerns to AnacortesReplacementProject@cngc.com or contact our Customer Service Center @ 1-888-522-1130 and a local representative will return your call within two business days


July 5, 2016

Cascade Natural Gas will begin Phase 4 of the Anacortes Pipeline Replacement Project resulting in the replacement of natural gas service lines in the area shown on the map. This is an ongoing program to ensure our customers of have safe and efficient natural gas service now and well into the future. During the construction phase crews will install mains and services in the designated areas on the map. There will be some disruption of streets, alleys and parking strips and this will be cleaned up daily.  Here is a brief outline of how this will impact your natural gas service:

  • The replacement of the natural gas service line will not result in any costs to the occupant/property owner
  • You will receive advance notification of any interruption to your natural gas service while your existing service line is retired/replaced
  • Our anticipated start date for construction is August 5, 2016
  • We anticipate completing construction at the end of October 2016
  • Please direct any concerns to AnacortesReplacementProject@cngc.com or contact our Customer Service Center at 1-888-522-1130 and a local representative will return your call within two business days
Anacortes Map of Phase 4 Area