Construction Ahead

Construction Projects

Cascade Natural Gas Corporation is in the process of replacing and updating service lines within our service territory. This is an ongoing program to ensure our customers safe and efficient natural gas service now and well into the future.

As a result of this construction, you may see some disruption of your normal traffic routes during the day. This construction activity will be kept as minimal as possible and will be cleaned up daily. Customers within the area of the replacement will be contacted regarding updating their lines and meters as the construction crew draws near. See below for more details about construction in your area.

Kelso, WA Pipeline Replacement Project

Construction on Phase 1 of the natural gas pipeline replacement project is tentatively scheduled to begin June 5th and complete in late October 2018.

For more information, please contact us by email at customerservice@cngc.com, by phone at (360) 577-4812, or speak with our field personnel on site at any time. We are committed to our community and your input is very important to us. All inquires are welcome and will be answered promptly.

See the outlined area on the map below for more detail on streets affected. Use CTRL + scroll on the map for a closer view.  

Shelton, WA Pipeline Replacement Project -  (Phase 2)

Construction on Phase II of the natural gas pipeline replacement project is tentatively scheduled to begin April 23 and conclude in late July 2018, weather pending.

For more information, please contact us by email at customerservice@cngc.com, or by phone at 888-522-1130, or speak with our field personnel on site at any time. We are committed to our community and your input is very important to us. All inquiries are welcome and will be answered promptly

See the outlined area on the map below for more detail on streets affected.  Use CTRL + scroll on the map for a closer view.  

Bend, OR - Westside Replacement Project (Phase 7)

Phase 7

Cascade Natural Gas Corporation is starting the Bend Westside Replacement Project Phase 7, Section 1/NW 14th Street on Monday 3/26/18. Crews will set up a traffic detour from NW Galveston Ave./NW Skyliners Rd. west to NW MT Washington Dr. Then north up NW MT Washington Dr. to NW Shevlin Park Rd./NW Newport Ave., and east on NW Shevlin Park Rd/ NW Newport Ave to NW 14th St. Once the traffic detour is in place, traffic on NW 14th Street south bound between NW Newport Ave. & NW Galveston Ave. will be closed to all traffic from March 26, through June 8, 24 hours a day. North bound traffic will remain open on NW 14th St. The south bound lanes will be used for construction equipment. The current plan is to open up traffic in both directions for the Memorial Day weekend and return to the current traffic plan until completion of Cascade’s current scope of work. For more about the NW 14th street Improvement project: www.BendOregon.gov/14thStreet.

Phase 7 Update - May 31, 2018

Crews working on the Bend Westside Replacement Project Phase 7 Section 1 are working in the alleys retiring old shallow crossings on NW 14th St . Pavers are scheduled for Monday 6/4/18. They will start at the intersection of NW 14th St. & NW Galveston Ave. and work north.  South bound lanes will remain closed until the end of Cascade Natural Gas’ portion of the project on Friday 6/8/18. 

Phase 7 Update - May 24, 2018

Crews working on the Bend Westside Replacement Project Phase 7 Section 1 will complete work on all crossings on NW 14th St. by Thursday 5/24/18. Both north & south bound traffic on NW 14th St. between Newport Ave. & NW Galveston Ave. will be open for the Memorial Day weekend. South bound lanes will close on Tuesday morning 5/29/18 and will remain closed until the end of Cascade Natural Gas’ portion of the project, which is expected to be Friday 6/8/18.   

Phase 7 Update - May 17, 2018

Crews on the Bend Westside Replacement Project Phase 7 Section 1 continue to work on crossings on NW 14th St. Crews will cross NW 14th St. at the roundabout with Galveston Ave. on Friday 5/18/18. Both northbound and southbound lanes will be closed on the north side of the roundabout at Galveston Ave. from 7 p.m. Friday evening to 7 a.m. Saturday. Both northbound and southbound traffic on NW 14th St between Newport Ave. & NW Galveston Ave. will be open for the Memorial Day weekend. Southbound lanes will close on Tuesday morning, 5/29/18, and will remain closed until the end of Cascade Natural Gas’s portion of the project on Friday 6/8/18.

Detour route noted in yellow:

Phase 7

Bend, OR - Pipeline Replacement (Phase 6)

Phase 6 Sections 1-2
Pipeline installation has been completed; asphalt and concrete restoration has been suspended until spring 2018.

Phase 6 Section 3 Update
Crews working on the pavement restoration on Bend Westside Replacement Project Phase 6 Section 3 are mid-block on NW Staats St. between NW Georgia Ave. & NW Florida Ave. Weather permitting, they should reach NW Florida on Friday, 4/6/18, and cross NW Florida Ave. Monday, 4/9/18, and continue toward NW Delaware Ave.  

Phase 6 Section 3 Update
Paving and final restoration on Bend Westside Replacement Project 3 Phase 6 Section is scheduled to begin Tuesday, 4/3/18. The paving crews will start at the intersection of NW Kansas Ave. & NW Staats St. and work south toward NW Delaware Ave. It is estimated to take about a week to reach NW Delaware Ave. Once the paving crews have reached the tie-in point on NW Staats St. between NW Delaware Ave. and NW Colorado Ave., the paving crews will move to the intersection of NW Georgia Ave. & NW Bond St. and work east.


Online Account Services

3 Choices Online Account