Construction Ahead

Construction Projects

Cascade Natural Gas Corporation is in the process of replacing and updating service lines within our service territory. This is an ongoing program to ensure our customers safe and efficient natural gas service now and well into the future.

As a result of this construction, you may see some disruption of your normal traffic routes during the day. This construction activity will be kept as minimal as possible and will be cleaned up daily. Customers within the area of the replacement will be contacted regarding updating their lines and meters as the construction crew draws near. See below for more details about construction in your area.

Bend, OR - Westside Replacement Project Phase 7 - Section 2


Update 9/6/18: Crews working on the Bend Westside Replacement Project Phase 7 - Section 2 are on NW 14th St. installing a 4-inch steel main. Crews are just south of NW Elgin Ave. and expect to cross NW Cumberland Ave. on Saturday 9/8/18.  NW 14th St. continues to be closed to all traffic between NW Commerce Ave. & NW Galveston Ave.

Update 8/30/18: Crews working on the Bend Westside Replacement Project Phase 7 Section 2 are currently in the alley between NW Davenport Ave. & NW Cumberland Ave. On Tuesday, 9/4/18, crews will move to the alley between NW Galveston Ave. & NW Fresno Ave. on the west side of NW 14th St and begin installing a 2-inch steel main. On Wednesday, 9/5/18, K&E Excavation will begin excavating a trench on the west side of NW 14th St. at the alley between NW Galveston Ave. & NW Fresno Ave. A crew will be working right behind K&E, installing a 4-inch steel gas main. Also a bore crew will be on the east side of NW 14th St. and begin boring north. The city of Bend’s contractor will shut down all traffic on NW 14th St.  (between NW Commerce Ave. & NW Galveston Ave.) beginning on Tuesday, 9/4/18, at which time Michels Pipeline Construction crews will begin installing a 4-inch steel gas main on NW 14th St. 


 

The Bend Westside Replacement Project Phase 7 Section 2 kicked off on Monday 8/20/18. The project is in conjunction with the city of Bend’s NW 14th St. reconstruction project.

Michels Pipeline Construction crews are currently working in the alleys on the west side of NW 14th St., working south from NW Galveston Ave. to NW Commerce Ave. As of Friday, 8/24/18, crews are in the alley between NW Baltimore Ave. & NW Cumberland Ave. and will move to the alley between NW Baltimore Ave. & NW Albany on Saturday 8/25/18. The alleys will remain closed at the intersection with NW 14th St. during the day and will be open by 5:30 each evening. These alleys will have local access only during the day from NW 15th St.

Once crews complete work on the west side, they will move to the east side of NW 14th St starting at NW Galveston Ave. and work south. Currently southbound traffic only is allowed on NW 14th St. between NW Commerce Ave. & NW Galveston Ave. The city of Bend’s contractor will shut down all traffic on NW 14th St (between NW Commerce Ave. & NW Galveston Ave.) beginning on Tuesday, 9/4/18, at which time Michels Pipeline Construction crews will begin installing a 4-inch steel gas main on NW 14th St.

See the outlined area on the map below for more detail on streets affected.

Bend, OR - Cascade Natural Gas Transmission Line Replacement

Update 9/6/18: Crews working on the Transmission Line Replacement project on SE Miller Ave. will complete the swabbing of the bore hole today, 9/6/18, and expect to pull pipe back through the bore hole on Friday, 9/7/18. Crews have strung out pipe on the north side of SE Miller Ave., blocking the intersections of SE Heyburn St and SE 4th St. As the pipe is pulled through the intersections, the intersections will be opened up to two way traffic. Once the pipe has been pulled through, crews will begin excavating trench, working east on SE Miller Ave. between SE 3rd St. & SE 4th St. Crews will be working on Saturday 9/8/16. Traffic on SE Miller Ave. will remain closed to through traffic. 

Update 8/30/18: Crews working on the Transmission Line Replacement project on SE Miller Ave. in Bend are currently back reaming their bore hole and expect to pull pipe back through the bore hole on 9/4/18 through 9/6/18. Crews will begin stringing out pipe on the north side of SE Miller Ave., blocking the intersections of SE Heyburn St. and SE 4th St. on Tuesday, 9/4/18. As the pipe is pulled through the intersections, the intersections will be opened to two way traffic.  Once the pipe has been pulled through, crews will begin excavating a trench, working east on SE Miller Ave. between SE 3rd St. & SE 4th St., which will remain closed to through traffic. Our contractor on this project, Northwest Metal Fab & Pipe, will begin notifying residents in the area, via a flyer of the upcoming intersection disruptions.

Update 8/24/18: Crews working on the transmission line replacement project on SE Miller Ave. are reaming a bore hole, and expect to pull pipe back through the bore hole on 8/29/18. Once the pipe has been pulled through, crews will begin excavating trench working east on SE Miller Ave. SE Miller Ave. between SE 3rd St. & SE 4th St. will remain closed to through traffic.



Cascade Natural Gas will start on Monday, Aug. 6, a transmission line replacement project in Bend. The bore crew will be mobilizing and setting up near the address of 224 SE Miller Ave. The equipment will be on the side of the street and should not affect the traffic flow. The duration of this project is expected to be approximately 8-10 weeks.

See the outlined area on the map below for more detail on streets affected. Use CTRL + scroll on the map for a closer view.

Kelso, WA Pipeline Replacement Project

Construction on Phase 1 of the natural gas pipeline replacement project is tentatively scheduled to begin June 5th and complete in late October 2018.

For more information, please contact us by email at customerservice@cngc.com, by phone at (360) 577-4812, or speak with our field personnel on site at any time. We are committed to our community and your input is very important to us. All inquires are welcome and will be answered promptly.

See the outlined area on the map below for more detail on streets affected. Use CTRL + scroll on the map for a closer view.  

Shelton, WA Pipeline Replacement Project -  (Phase 2)

Construction on Phase II of the natural gas pipeline replacement project is tentatively scheduled to begin April 23 and conclude in late July 2018, weather pending.

For more information, please contact us by email at customerservice@cngc.com, or by phone at 888-522-1130, or speak with our field personnel on site at any time. We are committed to our community and your input is very important to us. All inquiries are welcome and will be answered promptly

See the outlined area on the map below for more detail on streets affected.  Use CTRL + scroll on the map for a closer view.  


Online Account Services

3 Choices Online Account